How to Reinforce Wire Mesh for Concrete Slabs
- 1). Lay down slab runners across your pour area to support the mesh. If you are doing a slab on grade (the ground) skip this step (you add the wire mesh supports last). Slab runners support wire mesh in elevated concrete pours, you make them from welded wire supports in varying heights. Each runner is 4-feet long, and you will lay them down, one butted against the other to form support lines through your pour. Place each line of runner 3 1/2 feet from the next line of runners.
- 2). Lay your first sheet of mesh down on top of the slab runners (if you are working on a slab on grade simply lay the mesh on the ground). Begin in a corner making sure that you maintain the specified clearance for your project. Keep the metal away from the edge of a concrete pour. This prevents rust, from the metal in the concrete, from bleeding through to the exterior.
- 3). Carry your next sheet of wire mesh over and rest it on the edge of the first sheet you put down 1 1/2 squares onto the first sheet. Welded wire mesh is welded in squares, you want each sheet to overlap the other 1 1/2 squares. Place your foot through the bottom of the second sheet (that you are holding upright) and press down. Let the second sheet drop forward onto the slab runners. Adjust the second sheet so the edge overlapping the first sheet is straight and even, covering 1 1/2 squares of the first sheet.
- 4). Tie the sheets together. Use Linesman pliers to make tie wire snap ties at both corners of the overlapping sheets of wire mesh and place at least one tie in the center of the overlap. Make sure that the ties join the two sheets together. Continue laying down your wire mesh and tying it together until your entire slab is covered.
- 5). Raise the completed mesh to the correct height within the slab. If you have placed slab runners down you can skip this step as you already did this to begin the slab. Place 2x2 concrete bricks under the wire mesh every 4 feet to support the mesh.